• Login
    View Item 
    •   Home
    • Theses & Dissertations
    • 2021 - Mines Theses & Dissertations
    • View Item
    •   Home
    • Theses & Dissertations
    • 2021 - Mines Theses & Dissertations
    • View Item
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Browse

    All of Mines RepositoryCommunitiesPublication DateAuthorsTitlesSubjectsThis CollectionPublication DateAuthorsTitlesSubjects

    My Account

    Login

    Mines Links

    Arthur Lakes LibraryColorado School of Mines

    Statistics

    Display Statistics

    Predicting tunnel boring machine utilization using discrete event simulation models for hard rocks

    • CSV
    • RefMan
    • EndNote
    • BibTex
    • RefWorks
    Thumbnail
    Name:
    Khetwal_mines_0052E_12127.pdf
    Size:
    7.004Mb
    Format:
    PDF
    Download
    Author
    Khetwal, Anuradha
    Advisor
    Rostami, Jamal
    Date issued
    2021
    Keywords
    simulation
    tunneling
    discrete event simulation
    underground construction
    tunnel boring machine
    
    Metadata
    Show full item record
    URI
    https://hdl.handle.net/11124/176437
    Abstract
    Tunnel Boring Machines (TBM) are perhaps the most efficient method for tunnel excavation, as they have become the dominant mode and method of tunneling around the world. One of the essential steps for justification of the use of TBMs as well as planning the completion time and estimating the cost of projects involving TBMs is estimating the machine performance in given ground conditions. The main performance indicator for TBMs is the average daily advance rate (AR) which is product of rate of penetration (ROP), utilization (U). While there are various models for estimation of machine ROP with acceptable levels of accuracy and reliability, the models for prediction of machine utilization are often not sufficiently accurate and do not include many of the critical input information. This is because the predictive models for estimation of machine utilization do not have the capability to deal with many of the site-specific issues, including variation in geological settings, TBM and backup specifications, and site set up and logistics. Improving the accuracy of models for TBM performance prediction by estimation of utilization has been the focus of many ongoing studies in mechanized tunneling. It requires accounting for many factors including project geology, machine design and configuration, and operational issues. Simulation of tunnel activities considering TBM to be a tunneling factory can be a reliable method for estimation of TBM utilization factor. In this study, modeling tunneling activities and downtimes using discrete event simulation approach is adopted to predict TBM utilization. A few mechanized tunneling projects in hard rock have been considered for development of the model and verification of the results. A database template using visual basic for application (VBA) and data from available projects is established where the project and machine specifications along with the various geotechnical unit details serve as the input parameter for the simulation. The simulation model, CSM2020 is prepared using Arena© simulation software. The results of modeling were verified by comparing the estimated utilization with that of the recorded TBM utilization at the jobsites, broken down by formations and reaches of tunnel. This allowed for verification of the capabilities of the modeling concept to incorporate the impacts of geology and tunnel length. Sensitivity analysis of the model relative to certain activities allows for evaluating the ability of the simulation system to account for each activity and its impact on machine performance within a given geology and at certain reach of the tunnel. Parametric studies were conducted relative to various input parameters to the simulation model including geology, machine specification, and site set up to see the response of the model to various input parameters and to assess their impact on the utilization. The results were compared to some case histories for verification and proved that the modeling concept is functional. To apply the DES model to different projects, data recording, screening, and analysis protocols have been developed to allow for adjustment of the models with additional onsite input data. This approach was tried by both Arena© and the MATLAB code and site data for 8 different projects. The impact of interdependencies of various tunneling activities on machine utilization were also assessed to identify the critical activities that might act as bottlenecks in the excavation process. In parallel, a code was developed in MATLAB to allow for performing des modeling with better control of the process and data structure for individual activities and resources. The code also has the advantage that it does not require Arena© license to run and can be made into an executable program. In general, use of CSM2020 des model for utilization estimation prove to be a promising approach which can be further developed to include additional features and be expanded to variety of tunneling operation, while it can be further developed to be used as part of a system for optimization of tunneling operation and selection of TBMs with a quantitative approach to evaluate various features of the machine and backup system.
    Rights
    Copyright of the original work is retained by the author.
    Collections
    2021 - Mines Theses & Dissertations

    entitlement

     
    DSpace software (copyright © 2002 - 2022)  DuraSpace
    Quick Guide | Contact Us
    Open Repository is a service operated by 
    Atmire NV
     

    Export search results

    The export option will allow you to export the current search results of the entered query to a file. Different formats are available for download. To export the items, click on the button corresponding with the preferred download format.

    By default, clicking on the export buttons will result in a download of the allowed maximum amount of items.

    To select a subset of the search results, click "Selective Export" button and make a selection of the items you want to export. The amount of items that can be exported at once is similarly restricted as the full export.

    After making a selection, click one of the export format buttons. The amount of items that will be exported is indicated in the bubble next to export format.